Sunday, March 28, 2010

Appliances are installed and yard work begins (Week 21)







The plumbers came back this week and hooked up all the faucets, toilets, hot water heater, and installed the connections for the refrigerator and dishwasher. The replacement wood floors arrived on Tuesday, which after spending two days acclimating to the climate of the house, allowed for installation to start on Thursday. Tim has been splitting his time between the house and a remodel project at Valley Building Supply. Tim worked on the floors Thursday, Friday, and Saturday. He finished the installation in the living room, foyer, and most of the dining room. He just needs to finish the dining room, start the office, and the upstairs hallway. We also received in the wood stair treads, banister, and pilasters for the staircase. Early this week, or maybe it was late last week, the excavators finished moving the dirt that was stored on the adjacent lot and leveled up our back yard. We really needed the extra dirt, it looks great. After talking to several people I decided to take some advice of purchasing some compost from the local mushroom plant to amend the soil to help grass grow. They filled my 5x10 utility trailer so high that the mound was almost taller than my 4Runner. I bought 3 loads, one for the front yard and two for the back. I'm sure I could use a few more loads but it was so time consuming waiting in line that this might have to do. Katie and I assembled our new kitchen table that we ordered. It has been in boxes at her office and we couldn't stand waiting any longer with the kitchen so close. Billy, the electrician, is supposed to be back to finish up some of the final electrical work this week. I also expect Tim will finish up the wood floors. We moved a few boxes of plates and glasses to the house this week so we can start washing dishes while Tim is finishing up. We expect to move some more in next weekend over Easter weekend.

Friday, March 19, 2010

Granite, concrete, septic, and deck (Week 20)






I skipped writing an update last week because there wasn't much that I could show. This week however several big steps were completed. Early this week the granite counter tops were installed in the kitchen and master bath. They decided to cut the kitchen island out of a solid slab which weighted approximately 800lbs and took 7 guys to lift in place. Last week Tim started building the back deck, which he worked on today as well with the installation of the support posts and hand rail. All he has left to do on the deck is to install the pilasters below the handrail. Yesterday the excavators started digging the septic system. By lunch today they had the tank and all the fill lines in place and ready to start covering them back up, however the local city inspector took the day off and told them they couldn't do anything else until he looks at it on Monday. Jose has been working since last weekend painting the bonus room and repainting many of the rooms upstairs. I scheduled Bellsouth and Dish Network to install telephone and TV service today. By noon I had a little TV in my media closet playing satellite TV/radio while I wired the alarm system. Yesterday Katie and I received the master bedroom light we ordered. We found a really nice light we liked at the Pottery Barn however after scouring the internet we found the identical light for sale on Overstock.com for over $100 less than the Pottery Barn price. I stayed up last night putting it together and this morning the electrician installed it in our bedroom. The other big milestone was the pouring concrete in the garage and front porch. The concrete in the garage was 4-6in thick and they did a good job finishing the concrete and providing a gentle slope. The HVAC has been up and running the last two weeks which makes it nice to come in and work on the house in comfort.
Next Monday the plumbers are scheduled to come in and complete the finish plumbing including installation of the water heater, toilets, and faucets. Tim ordered all of the supplies for the staircase and they should be ready to be installed next week as well. Tim had previously stopped installation of our wood floors because of a concern with how the ends of the boards fit together. Turns out the manufacturer was out of our floors so they shipped wood to the factory in Alabama to be milled and finished. The new floors should arrive on Tuesday and Tim is guessing he will have them installed by Thursday. Today was an exciting day with all the work that was going on. Tim has discussed possibly being done in about two more weeks which has Katie and I really excited to consider starting to move in. It is close!

Sunday, March 7, 2010

Let there be light (week 18)




I don't have many pictures this week but we reached another major milestone with the connection of temporary power on Friday. I pulled up to the house on Friday morning to find Sweetwater Utilities Board working to pull wire from the transformer to our meter box on the side of the house. To my surprise they brought with them a new street light! I have been calling the city planner for 6 weeks and all I got was "I don't know", "I have to much paperwork on my desk to look", and "No, there aren't any more left", even though I knew there were. Luckily last week I talked to Delane Dacus, who we bought the lot from, who then talked to Mr. Plemons the original developer of the neighborhood. Apparently Mr. Plemons helped our city planner find the time to locate the lights because while the utility board guys were there they told me they found 10 more lights and they were going to go ahead and place them around the neighborhood. Friday night Katie and I went back to the house once it was dark and we got to see the house inside and out with all the lights turned on. I can't believe I didn't take a picture. All the rooms look like they have enough light except for maybe the master bathroom. We can always go back and add can lights in this location. I was also pleased when I pulled up Saturday morning to find a bulldozer moving lots of dirt. They moved some dirt on Monday to start getting the driveway up to grade. Saturday they finished grading out the driveway, adding dirt in front of the house, adding and sloping dirt on the side of the house, and adding dirt in the back yard to level out the yard immediately behind the house. We still need one full day of grading to finish up. The forecast is looking good for Monday and Tim has alot planned while the weather is good. Tim is planning on installing the back elevated deck and the HVAC guys are scheduled to install the heat and air on Monday. Tim is also working with the excavators to install the septic tank and fill lines. The counter top crew should be back early next week to install the granite and then the plumbers can do final tie-in. We are getting really close now that final connections are being made. Tim has been holding off on putting more of the wood floors in until all the subs finish their interior work to ensure they don't get scratched up.